Produce labour and material schedules for ordering

KHU-CON-0008

Australian Equivalent
CPCCBC4005
Elements
3
Learning Outcomes
14

This unit of competency specifies the skills and knowledge required to produce schedules for physical and human resources and materials for residential or commercial projects. It includes monitoring project schedules and tracking and recording costs as they are incurred. This unit of competency applies to site managers and forepersons, estimators, project managers and builders in the construction industry with responsibility for producing schedules for ordering materials and allocating labour. This unit of competency is suitable for those using specialised knowledge to complete routine and non-routine tasks and using their own judgement to deal with predictable and sometimes unpredictable problems. Completion of the general construction induction training program specified by the model Code of Practice for Construction Work is required for any person who is to carry out construction work

Elements & Learning Outcomes

3
E1Assess physical and human resource requirements.
0008.E1.O1Check conditions of approval from local government and regulatory bodies and project commencement dates.
0008.E1.O2Identify variations to scope of works and contractual terms and arrangements by the client.
0008.E1.O3Compile a list of nominated and approved suppliers and contractors and develop channels for effective communication.
0008.E1.O4Confirm availability of materials with suppliers and labour with contractors.
0008.E1.O5Enter critical project information into project schedule.
E2Produce schedules.
0008.E2.O1Prepare electronic call forward sheet and site files containing necessary site documentation.
0008.E2.O2Break down project into stages and tasks and set milestones and timeframes for commencement and completion.
0008.E2.O3Itemise materials and labour required for the stages of construction.
0008.E2.O4Sequence material delivery dates and commencement times for labour.
0008.E2.O5Factor in unplanned delays.
E3Monitor project costs and maintain project files.
0008.E3.O1Monitor construction stage progression costs and approved variation costs against estimated project cost.
0008.E3.O2Manage and monitor project progress against scheduled timelines.
0008.E3.O3Record unscheduled and approved variations, changes to the approved plan and specifications and delays to the project.
0008.E3.O4Resolve issues, within scope of responsibilities, and maintain a cost analysis against final estimated project cost.
SEAL — South East Asia Learning Identifier & Skills Portal · Prepared for MLVT Executive approval and TVET institute review · Derived from the Australian National Training Register (training.gov.au, CC-BY) and aligned to the Cambodian Qualifications Framework and DSC Standard Training Packages · Delivered via Gibble SMS · July 2026