Work safely on scaffolding higher than two metres

KHU-CON-0137

Australian Equivalent
CPCCCM2010
Elements
4
Learning Outcomes
18

This unit of competency specifies the outcomes required to work safely on construction sites where the work activity involves working above two metres from ground level and where fall protection measures are required. It covers safe methods for accessing the work site; and safe methods of moving or passing tools, equipment and materials to heights above two metres, including handling methods that avoid excessive bending or twisting. The unit supports construction workers operating from scaffolding over two metres in height that has already been constructed with signage and exclusion barriers in place, in order to reach upper storeys or roofs of buildings. It applies to workers who need to control the risk of falling and of falling objects when working on site or removing scaffold components. It applies to construction work on residential and commercial work sites in new construction, ren

Elements & Learning Outcomes

4
E1Identify work requirements.
0137.E1.O1Site of proposed work at heights is identified from relevant information.
0137.E1.O2Tasks to be completed are identified from work orders and supervisor instructions.
0137.E1.O3Personal protective equipment (PPE) suitable to the job is selected and checked for serviceability.
0137.E1.O4Method of accessing work area is identified according to safe work method statement (SWMS).
0137.E1.O5Safe work methods for moving tools, equipment and materials to work area are identified to minimise risks.
0137.E1.O6Verbal and non-verbal communication signals are confirmed with team members, supervisor and other personnel working on site, as required.
E2Access work area.
0137.E2.O1Work site is inspected and conditions and hazards are assessed and reported, as required, and risk controls selected according to SWMS.
0137.E2.O2Safety of scaffolding is checked and faults are reported to relevant personnel.
0137.E2.O3Arrangements are made to install required access equipment according to SWMS.
0137.E2.O4Access equipment is inspected for defects and issues are reported and rectified according to health and safety requirements.
0137.E2.O5Safe work methods are used to access work area and to move tools, equipment and materials to required locations on the work site.
0137.E2.O6Tools and materials are placed to eliminate or reduce the risk of items falling.
E3Conduct work tasks.
0137.E3.O1Work is conducted following workplace-approved procedures and SWMS.
0137.E3.O2Communication with team members and other site personnel is maintained as required to progress work tasks according to required timelines.
0137.E3.O3Fall protection equipment is kept in place and adjusted to cater for movement during work.
0137.E3.O4Scaffold components and fall barriers are kept in place during work.
E4Finalise work processes.
0137.E4.O1Egress from work area is completed following SWMS and work site supervisor approved methods for moving self, tools and materials to ground level.
0137.E4.O2Tools, equipment and materials returned to ground level are cleaned, checked, maintained and stored according to manufacturer specifications.
SEAL — South East Asia Learning Identifier & Skills Portal · Prepared for MLVT Executive approval and TVET institute review · Derived from the Australian National Training Register (training.gov.au, CC-BY) and aligned to the Cambodian Qualifications Framework and DSC Standard Training Packages · Delivered via Gibble SMS · July 2026