Install bulk insulation and pliable membrane products

KHU-CON-0244

Australian Equivalent
CPCCPB3014
Elements
4
Learning Outcomes
25

This unit specifies the outcomes required to safely undertake floor, wall and ceiling insulation installation work using bulk insulation and pliable membrane products. The unit includes identifying legislative, regulatory, and job requirements;planning and preparing to install insulation; installing insulation; and, completing installation, including preparation of a Statement of Insulation Installation. The unit requires a person undertaking this work to comply with legislative, regulatory, safety and technical, organisational and site requirements while planning and carrying out the work. The unit applies to insulation installers working primarily in residential buildings, although there may be application in some instances in commercial buildings. The work context involves working at heights, working in enclosed areas, dust control and mitigation of risk from asbestos. At the time of

Elements & Learning Outcomes

4
E1Define job Requirements
0244.E1.O1Identify scope of required installation activities through review of job requirements and inspection of work site.
0244.E1.O2Assess and control site risks and hazards and communicate and clarify any issues with supervisor.
0244.E1.O3Identify requirements of workplace procedures for responding to the presence of vermin, asbestos, and dust within the workspace.
0244.E1.O4Identify required safety equipment and processes by review of work order, risk assessment, safety data sheets (SDS), safe use instruction sheet (SUIS) and safety legislation.
0244.E1.O5Identify and review requirements of Australian Standards (AS) AS 4200.2 for pliable membrane wall insulation and AS 3999 relating to electrical inspections, safety and installation activities.
0244.E1.O6Identify and review workplace environmental requirements that relate to the installation activities.
0244.E1.O7Identify and review workplace emergency response and evacuation procedures as they apply to the site of the installation activities.
0244.E1.O8Identify and review work instructions and specifications that relate to the installation activities.
E2Plan and prepare for installing insulation.
0244.E2.O1Undertake an electrical risk assessment and prepare an electrical risk assessment report.
0244.E2.O2Document and submit for approval a Safe Work Method Statement (SWMS) for the worksite, incorporating identified risks and hazards, the outcomes of the electrical risk assessment, electrical isolation procedure and the hazard hierarchy of control.
0244.E2.O3Plan job incorporating identified requirements of work order, work site, safety legislation, AS 3999, environmental requirements, work instructions and specifications and SWMS.
0244.E2.O4Confirm that insulating material and insulation requirements meet work instructions and thermal and acoustic performance specifications.
0244.E2.O5Put in place all requirements of the SWMS.
0244.E2.O6Select personal protective equipment (PPE), tools, equipment and associated materials, check for serviceability and report for repair or replacement where unserviceable.
E3Install floor, wall and ceiling insulation.
0244.E3.O1Isolate worksite electrical circuits and install safety signage and lock-out tag in accordance with the SWMS.
0244.E3.O2Undertake installation work in accordance with the SWMS.
0244.E3.O3Undertake installation work using approved methods of measurement and cutting of insulating material.
0244.E3.O4Undertake installation work in accordance with requirements of AS 3999 for recessed luminaries and electrical cable and AS 4200.2 for wall applications where pliable building membranes are required.
0244.E3.O5Undertake installation work in accordance with manufacturers’ specifications and minimise waste.
0244.E3.O6Install insulation without damage or distortion of the surrounding environment, electrical and other services and in a manner that maximises safety of self and others.
0244.E3.O7Conduct final inspection to ensure installed floor, wall and ceiling insulation conforms to work instructions, AS 3999 and manufacturers’ specifications.
E4Complete installation.
0244.E4.O1Clean work area and dispose of, re-use or re-cycle materials following workplace and environmental procedures.
0244.E4.O2Clean, check, maintain, and store tools and equipment in accordance with manufacturer specifications.
0244.E4.O3Document details of malfunctions, faults, wear or damage to tools and equipment and report for repair or replacement.
0244.E4.O4Document, distribute, and store Statement of Insulation Installation.
SEAL — South East Asia Learning Identifier & Skills Portal · Prepared for MLVT Executive approval and TVET institute review · Derived from the Australian National Training Register (training.gov.au, CC-BY) and aligned to the Cambodian Qualifications Framework and DSC Standard Training Packages · Delivered via Gibble SMS · July 2026