Lesson 3.3 — Wiring the Power Room
Connection order protects equipment and installer: battery to controller FIRST (controller learns system voltage), then panels to controller, then inverter directly to battery through its own fuse — never through the controller's load terminals. Batteries sit in a ventilated box off the floor; lead-acid vents hydrogen, so no sparks, no smoking, terminals covered. Fuse every battery positive within 30 cm of the terminal.
Reversing battery polarity kills controllers and inverters instantly — check twice, connect once.
Evidence task
Upload photos of your completed power-room wiring with labels visible.